12 labours can build a wall in 24 days. how long will 8 labours take to build the sme wall ?


if 12 laborers take 24 days build wall, wall require (12 x 24) 288 man days construct. if 8 laborers used build same size wall take 288 man days divided 8 men or 36 days.

suggested take 32 days 8 men build same size wall, able complete (8 x 32) = 256 man days of work not required 288 man days. 32 man days short of being complete. 32 divided 8 equal 4 more days complete. surprise, surprise 32 man days plus 4 additional man days equals 36 man days suggested.

or 8 divided 12 equals 8/12 or 2/3 or 0.66666 amount of original work force. means perform 2/3 amount of work in same time frame (24 days ). 8 laborer crew therefore have work 3/2 (1.5) time complete same amount of work 12 laborer crew. 24 days required 12 laborer crew times 1.5 equal 36 days 8 laborer crew. surprise, surprise.

worth laborers build masonry walls, concrete , framed walls. masons build block , brick walls , carpenters build framed walls , forms concrete walls. although have other principle tasks assist masons, carpenters, electricians, mechanical, etc. trades. don't build walls.

12 labours can build wall in 24 days. how long 8 labours take build sme wall ?


Home & Garden Do It Yourself (DIY) Next



Comments

Popular posts from this blog

SOMEONE WITH COMPUTER KNOWLEDGE PLEASE HELP ME!?

Songs about wanting to forget someone?

What is the point of New Year's Day?